Person 1 is thrice as good a workman as person 2 and so takes 30 days less than person 2 for doing a job. Calculate the time in which they can do the job together is.
11 1/4
12
11
12 1/2
20
Option A Let person 1 can finish the whole work in x days. Person 2 can finish the same work in 3x days. then 3x-x= 2x= 30 x= 15 days Person 1 can finish the work in 15 days. Person 2 can finish in 45 days. A+B work = 1/15 + 1/45 = 4/45 A+B can finish the work in 45/4 = 11 ¼ days
32 men and 24 women together can complete a work in 16 days. 40 men can complete the same work in 32 days.How many days will 32 women can complete the same work ?
10
12
15
20
18
Option D (32 M + 24 W)* 16= 40 M * 32 = 40M * 16 * 2 32M + 24W = 80M 24W =48M 1W=2M-------1 32W=64M-----2 Now 40 men complete the work in 32 days. So 64 men complete the same work in 32* 40 / 64 = 20 days. Hence 32 women complete the same work in 20 days.
Four examiners can examine a certain number of answer papers in 10 days by working for 5 a day. for how many hours in a day would 2 examiners have to work in order to examine twice the number of answer papers in 20 days?
2 boys and 3 girls together or 4 boys can complete a piece of work in 20 days. 3 boys and 3 girls will complete the same work in how many days?
15
16
17
18
19
Option B 2 boys + 3 girls= 4 boys =>2 boys = 3 girls =>3 boys + 3 girls = 5 boys ( 3 girls= 2 boys) M1D1= M2D2 =>4* 20 = 5 *D2 D2 = 16 days.
Varun gets Rs. 700 for every day that the works. If he runs Rs.19600 in a month of 62 days, for how many days did he work?
21
20
23
28
25
Option D Varun gets Rs.700 for 1 day of work Amount received by varun for 62 days. Number of days Varun worked in a month = 19600/ 700 =28 days.
Person A and Person B can complete a piece of work in 30days and 20 days respectively. Then contracted to complete the work for Rs. 60,000.The share of Person A in the contracted money will be
24,000
25,000
20,000
19,000
26,000
Option A Total amount = Rs.60,000 Person A’s 1 day work = 1/30 Person B’s 1 day work =1/20 Ratio = 1/30 : 1/20 = 2:3 Sum of the ratio = 2+3 = 5 Person A’ s share = 2/5 * 60,000 = Rs.24,000
There are n number of workers can finish a project work in 15 days. If there are 3 workers could be finished in 5 days less. the original number of workers are:
3
5
7
4
6
Option E M1M2=M2D2 n*15 = ( n+3) * 10 n=6
84 women can do a piece of work in 36 days. How many women are required to complete the same work in 42 days?
72
36
78
44
67
Option A 84 women -- 36 days 1 women--84 * 36 days Number of women required = 84 * 36/42 = 72 women
Person A earns Rs. 250 in 16 days and person B earns Rs.280 in 20 days. what is the ratio of their earnings?
25:112
12:112
120:112
125:112
125:110
Option D Required ratio = 250/16 : 280/ 20 =5000:4480 =125:112
Hasini and her daughter received Rs. 800 as wages for 5 days work. Hasini’s work was three times more efficiency han her daughter. Then what is the daily wage of her daughter?